CONSTRUCTION SITE PROGRESS

Know what happened on site, every day.

Record daily site activities, actual quantities, photos, manpower and other site information to keep project progress clear and up to date.

Plan the Work → Execute → Record the Progress → Control the Cost → Bill the Customer

PROJECT CONTROL · SITE PROGRESS

PRJ-00184 · Al Barsha Heights Villas

Site: Al Barsha South, Dubai · Diary date: 14 Sep 2026

+ Add progress

Today's activities

4 of 6

Completed quantity today

145 m² · 36 Points

Overall project progress

42%

Sample Masarek site progress record showing daily construction activities, completed quantities and progress
ActivityUnitCompleted todayTotal completedProgress
Block Workm²85290
64%
Plasteringm²60210
35%
Electrical WorksPoints2478
65%
Plumbing WorksPoints1244
48%
Flooringm²00
0%
Paintingm²00
0%

Manpower

Mason 6 · Helper 8 · Electrician 3 · Plumber 2

Materials

Cement 40 bags · Blocks 320 Nos

Photos

6 photos attached

Note: Block A ground floor slab poured and cured. Block B exterior blockwork reached 2.4 m. First-fix electrical rough-in continued.

DAILY SITE PROGRESS

Turn daily site activity into a clear record.

Construction work changes every day. Record what was planned, what was completed and what happened on site in a structured daily record.

01

Work activities

Record the construction activities carried out on site during the day.

02

Completed quantities

Enter the quantity completed for each activity in its own unit.

03

Manpower

Record the trades and number of workers present on site.

04

Materials

Note the materials consumed or delivered for the day's work.

05

Equipment

Log the equipment used and the hours it worked.

06

Site expenses

Capture small site expenses against the project record.

07

Photos

Attach site photos to the activity they belong to.

08

Notes

Add site notes about conditions, delays or instructions.

09

Attachments

Keep supporting files with the day's progress record.

PROJECT CONTROL · SITE PROGRESS

PRJ-00184 · Al Barsha Heights Villas

Site: Al Barsha South, Dubai · Diary date: 14 Sep 2026

+ Add progress

Today's activities

4 of 6

Completed quantity today

145 m² · 36 Points

Overall project progress

42%

Sample Masarek site progress record showing daily construction activities, completed quantities and progress
ActivityUnitCompleted todayTotal completedProgress
Block Workm²85290
64%
Plasteringm²60210
35%
Electrical WorksPoints2478
65%
Plumbing WorksPoints1244
48%

Manpower

Mason 6 · Helper 8 · Electrician 3 · Plumber 2

Materials

Cement 40 bags · Blocks 320 Nos

Photos

6 photos attached

Note: Block A ground floor slab poured and cured. Block B exterior blockwork reached 2.4 m. First-fix electrical rough-in continued.

Completed work

Record the work completed on site.

Capture actual construction activities and quantities as work progresses. Keep project managers and office teams informed about what is happening on site.

Activity progress

Block Work

Diary 14 Sep 2026
Planned quantity
450 m²
Completed today
85 m²
Total completed
290 m²
Remaining
160 m²
64%

Activity progress

Electrical Works

Diary 14 Sep 2026
Planned quantity
120 Points
Completed today
24 Points
Total completed
78 Points
Remaining
42 Points
65%

Sample construction data shown to demonstrate the interface — not customer results.

Actual quantities

Track actual quantities.

Record the quantities completed on site and compare them with the planned quantities to understand actual project progress.

PLANNED

450 m²

Block Work · Building B

COMPLETED

290 m²

Block Work · Building B

REMAINING

160 m²

Block Work · Building B

Actual quantity tracking

PRJ-00184 · Planned vs completed

Sample planned versus completed construction quantities by activity
ItemPlannedCompletedRemainingProgress
Concrete310 m³212 m³98 m³
68%
Block Work450 m²290 m²160 m²
64%
Plastering600 m²210 m²390 m²
35%
Flooring580 m²0 m²580 m²
0%
Painting1,850 m²0 m²1,850 m²
0%
Electrical Points120 Nos78 Nos42 Nos
65%

Quantities are entered by your site team — recorded figures feed actual quantity and cost tracking.

Recorded quantities connect directly with actual quantity and cost tracking in Masarek.

Activity progress

See progress by activity.

Get a clear view of which construction activities are completed, in progress or still pending.

CompletedIn ProgressPendingDelayedPRJ-00184 · Activity progress
  • Foundation Works

    Closed 12 Sep 2026

    100%
    Completed
  • Block Work

    Building B · Zone 2

    65%
    In Progress
  • Plastering

    Block A internal walls

    35%
    In Progress
  • Electrical

    First-fix rough-in

    50%
    In Progress
  • Plumbing

    Waiting for material delivery

    22%
    Delayed
  • Flooring

    Not Started

    0%
    Pending

Status and progress are updated by your team from the recorded site entries.

Photos & notes

Keep photos and site notes together.

Add photos and notes to daily progress records so the project team can review site conditions and completed work with the right context.

Construction workers plastering internal walls on a Masarek site progress record
Plastering14 Sep 2026

Block A · Ground Floor

Internal wall plastering in progress on the ground floor.

First-fix electrical and mechanical rough-in captured in a site progress photo
Electrical Works14 Sep 2026

Block B · First Floor

First-fix electrical rough-in above the ceiling line.

External blockwork progress photo attached to a daily construction site record
Block Work13 Sep 2026

Block B · External Walls

External blockwork reached 2.4 metres on the south elevation.

Site resources

Know what was happening on site.

Keep daily visibility of the people, materials and equipment involved in project execution.

MANPOWER

Mason
6 · 10 hrs
Helper
8 · 10 hrs
Electrician
3 · 9 hrs
Plumber
2 · 9 hrs

MATERIALS

Cement
40 bags
Blocks
320 Nos
Tiles
60 m²
Cable
180 m

EQUIPMENT

Mixer
1 · 6 hrs
Generator
1 · 10 hrs
Cutting Machine
2 · 4 hrs

Progress & cost

Connect site progress with project cost.

The work completed on site helps you understand how the project is progressing against its planned quantities and costs.

Planned Work

Site Progress

Actual Quantity

Actual Cost

Project Control

Site Progress works as part of Masarek's wider project and cost-control workflow, alongside Schedules & Tasks, procurement, project management and billing.

From the site

Record progress from the site.

Use the Masarek mobile app to capture daily activities, quantities, photos, notes and other site information while the work is happening.

  1. 01

    Select Project

  2. 02

    Select Activity

  3. 03

    Enter Quantity

  4. 04

    Add Photos

  5. 05

    Add Notes

  6. 06

    Save Progress

Masarek · Site Progress

Project

Al Barsha Heights Villas

Activity

Block Work

Completed today

85 m²

Note

South elevation reached 2.4 m.

Save Progress

BUILT FOR CONSTRUCTION

Made for the way construction work happens.

From small contractors to larger construction teams, keep daily project progress organized and visible across the office and site.

01

General Contractors

Record the day's activities, quantities and photos in one project record.

02

Subcontractors

Record the day's activities, quantities and photos in one project record.

03

MEP Contractors

Record the day's activities, quantities and photos in one project record.

04

Fit-Out Companies

Record the day's activities, quantities and photos in one project record.

05

Civil Contractors

Record the day's activities, quantities and photos in one project record.

06

EPC Contractors

Record the day's activities, quantities and photos in one project record.

07

Renovation & Remodeling Companies

Record the day's activities, quantities and photos in one project record.

08

Engineering & Construction Companies

Record the day's activities, quantities and photos in one project record.

09

Design & Build Companies

Record the day's activities, quantities and photos in one project record.

Connected workflow

From project plan to actual progress.

Site Progress is part of the connected Masarek construction workflow, helping teams move from planning the work to recording what was actually completed.

01

Lead

02

Site Visit

03

Estimation

04

Quotation

05

Project

06

Schedule & Tasks

07

SITE PROGRESS

08

Procurement & Execution

09

Actual Quantity & Cost

10

Billing & Invoice

Plan the work. Execute the work. Record the progress. Control the cost. Bill the customer.

Connected with Schedules & Tasks · Estimation & Quoting · Digital Takeoffs · Masarek product · Pricing

One view

One clear view of site progress.

Keep daily site records, completed quantities, activities and project progress connected in one place.

SITE PROGRESS OVERVIEW

PRJ-00184 · Al Barsha Heights Villas

Al Barsha South, Dubai · Updated 14 Sep 2026

Project progress

42%

Completed quantity

290 m²

Pending work

160 m²

Site entries this month

18

Recent site entries

Recent Masarek site progress entries with date, activity, area, completed quantity and recorded by
DateActivityAreaQuantityRecorded by
14 Sep 2026Block WorkBlock B · Zone 285 m²Fazal Rahman
14 Sep 2026Electrical WorksBlock B · First Floor24 PointsHani Sabri
13 Sep 2026PlasteringBlock A · Ground Floor60 m²Yusuf Karim
13 Sep 2026Plumbing WorksBlock A · Toilets12 PointsNabil Fares

Activity status

  • Foundation Works

    100%
  • Block Work

    65%
  • Electrical

    50%
  • Plastering

    35%
  • Flooring

    0%

Photos & site notes

Masarek site progress photo 1Masarek site progress photo 2Masarek site progress photo 3

"Block B south elevation reached 2.4 m. Plumbing material delivery pending."

Sample project data shown for illustration — your own projects, activities and quantities are used in Masarek.

Questions & answers

Frequently asked questions

Can site teams record daily progress?

Yes. Site teams record daily progress, manpower, activities, photos and site events so the office has a current record instead of scattered messages.

Does site progress connect to cost and billing?

Yes. Recorded progress supports cost control and gives a basis for invoicing completed work rather than relying on estimates after the fact.

READY TO CONNECT?

Keep every day's work on record.

Record site activities, capture actual progress and keep your construction projects under control with Masarek.